22 Issues with Acid Mine Drainage in the Appalachians
Tuesday, 21 March 2006
8:00 AM - 12:00 PM
TREATMENT OF PYRITE-GENERATED POLLUTION
Paper number: 22-11
Program: THEME SESSIONS
Time: 11:20 AM – 11:40 AM
Authors
-
Scott NuttAltoona, PA
Abstract
Tests were carried out with slurry treatment in 10 ton tank samples and 50 lb column samples of aggregate from I-99 roadcuts. Additives used were 325 mesh limestone, periclase, and kaolinite in different proportions. Neutralization was achieved routinely with low concentrations of solids. Sulfate control resulted from the precipitation temporaarily of green rust and more persistently of gypsum. Penetration of the aggregate and partial coating of pyrite surfaces depended on clay concentrations. Practical methods of applying the slurry treatment are more challenging than the geochemical problems.