T219 Physical, Chemical, and Biological Controls on Remediation of Chlorinated Solvents in Fractured Rock
Wednesday, 25 October 2006
1:30 PM - 5:30 PM
TIME OF REMEDIATION ESTIMATES AT A NAPL-CONTAMINATED FRACTURED-ROCK SITE
Paper number: T219-7
Program: Technical Sessions
Time: 3:00 PM – 3:15 PM
Authors
-
Eduardo MendezVirginia Tech, Blacksburg, VA
Abstract
The objective of this research is to estimate time of remediation at a contaminated site in which contaminants from an industrial facility have entered the upper part of a 52-m thick dolomite aquifer. Trichloroethene (TCE) and other chlorinated ethenes are present as an aqueous phase plume derived from a well-defined source of dense non-aqueous phase liquid (DNAPL). The on-going remediation strategy involves a combination of pump-and-treat and MNA. NAS simulation results suggest that while the multi-well pumping system has decreased concentrations of TCE in groundwater, the cleanup timeframe is not significantly different between MNA-only and the current strategy.