38 The 2005 Taum Sauk Reservoir Breach: Failure Mechanisms, Flood Effects, Bedrock Exposures, and Current Remediation Efforts
Tuesday, 13 April 2010
10:00 AM - 12:00 PM
Short Creek 2
UPPER TAUM SAUK RESERVOIR FOUNDATION PREPARATION AND GEOLOGY
Paper number: 38-8
Program: Theme Sessions
Time: 11:45 AM – 12:00 PM
Authors
Abstract
The reservoir was re-built with 2.8 million cubic yards of Roller Compacted Concrete (RCC). The materials from the original dam were used in the RCC mix. The foundation is 1.5 billion year old Precambrian Rhyolite Porphyry, which has been intruded by 1.1 billion year old diabase dikes. Along the contacts of these dikes the diabase is altered to a range of materials from sandy silt to clay. Identification, engineering analysis, and treatment of these saphrolitic “clay seams”, along with detailed foundation preparation were the focus of the engineering geologic work on the project. The project was completion in February 2010.