38 The 2005 Taum Sauk Reservoir Breach: Failure Mechanisms, Flood Effects, Bedrock Exposures, and Current Remediation Efforts
Tuesday, 13 April 2010
10:00 AM - 12:00 PM
Short Creek 2
OVERVIEW AND HISTORY OF THE TAUM SAUK PUMPED STORAGE PROJECT
Paper number: 38-1
Program: Theme Sessions
Time: 10:00 AM – 10:15 AM
Authors
-
J. David RogersMissouri University of Science & Technology, Rolla, MO
-
Jae-won ChungMissouri University of Science & Technology, Rolla, MO
-
David J. HoffmanMissouri University of Science & Technology, Rolla, MO
Abstract
The upper reservoir was formed by blasting the top of
Prior to 1994 when the electric power industry was deregulated, the plant was operated approximately 100 days per year. Electric utilities were allowed to sell power on the spot market to other utilities at unregulated rates, making operations at the plant profitable up to 300 days a year. The plant’s massive pump-turbine units were replaced with higher efficiency models. By 2004, leaks through the cracked reservoir liner resulted in ~2% lost capacity per day, so a geomembrane liner was installed to curtail the losses. The reservoir’s water level gages, which were used to activate and shutdown the pumps, were also replaced and played a role in the failure.
At least two overtopping incidents occurred 11 weeks prior to the Dec 2005 failure, one of which was described as “Niagara Falls” by plant operators. This overflow resulted in noticeable scour of the embankment crest, requiring repairs. A less serious overtopping incident occurred a few days later, which was not directly observed. The new instrumentation conduits worked themselves loose and experienced severe deflections that registered erroneous stage levels. Although operators warned of continued use, a workaround was instituted and repairs were postponed.