BUILDING ON KARST - A BRIEF HISTORY OF GATHRIGHT DAM
Paper number: T50-9
Program: Technical Sessions
Time: 3:30 PM – 3:45 PM
Authors
-
Robert CannonSchnabel Engineering, Greensboro, NC
-
Alex RutledgeSchnabel Engineering, Greensboro, NC
-
Philip WunderlyNorfolk, Norfolk, VA
-
Gerald RobbleeSchnabel Engineering, Greensboro, NC
-
Raymond DridgeNorfolk, Norfolk, VA
-
Fred SniderSchnabel Engineering, Greensboro, NC
Abstract
This presentation will cover a case history of the treatment that was completed on the embankment foundation and abutment bedrock at Gathright Dam. Treatment methods included 30-foot deep consolidation grouting and 150-foot deep curtain grouting in the foundation and both abutments. In addition to the grouting, an 800-foot long concrete membrane wall was constructed in the left abutment to isolate extensively solutioned bedrock layers.