T20 Construction and Geology of the Massachusetts Water Resources Authority Tunnel, Eastern Massachusetts I
Monday, 5 November 2001
8:00 AM - 12:00 PM
IDENTIFYING AND MANAGING GEOLOGIC RISKS IN UNDERGROUND CONSTRUCTION–THE METROWEST TUNNEL AS AN EXAMPLE
Paper number: T20-3
Program: Technical Sessions
Time: 8:00 AM – 12:00 PM
Authors
Abstract
With the completion of tunnel excavation, it is now possible to reflect on the effectiveness of these methods. The high cost of more intensive and specialized explorations must be weighed against the uncertainty of the project geology and the potential for construction problems. On the MetroWest tunnel, the decision to spend additional time and money in the exploration phase on tunnel sections where the geology was suspect proved fruitful in that potentially higher construction costs were avoided. Suggestions for further improvements in identifying the risk of uncertain geologic conditions on future tunnels will be made.