33 Lake Research and Monitoring Networks in the Northeast (Posters)
Monday, 19 March 2018
8:00 AM - 12:00 PM
Lake Champlain Exhibition Hall
SEDIMENT RESUSPENSION AND COMPLIANCE MONITORING FOR THE NYPA/VELCO PV-20 SUBMARINE CABLE REPLACEMENT PROJECT
Paper number: 33-4
Program: Theme Sessions
Time: 8:00 AM – 12:00 PM
Authors
-
Timothy FollensbeeVELCO, Rutland, VT
-
Jason GormanCHA Companies, Albany, NY
-
Zack ClarkVHB, South Burlington, VT
-
Robert AthanVHB, South Burlington, VT
Abstract
This paper provides a summary of the pre-project planning and studies, project work completed, sampling methods, results of the 2017 monitoring compared to model predictions, and also provides an overview of the regulatory processes and mechanisms in place to maintain water quality within Lake Champlain from an industry perspective.
Geological Society of America Abstracts with Programs. Vol. 50, No. 2
doi: 10.1130/abs/2018NE-310809
© Copyright 2018 The Geological Society of America (GSA), all rights reserved. Permission is hereby granted to the author(s) of this abstract to reproduce and distribute it freely, for noncommercial purposes. Permission is hereby granted to any individual scientist to download a single copy of this electronic file and reproduce up to 20 paper copies for noncommercial purposes advancing science and education, including classroom use, providing all reproductions include the complete content shown here, including the author information. All other forms of reproduction and/or transmittal are prohibited without written permission from GSA Copyright Permissions.