229 D1. Recent Advances in Economic Geology
Wednesday, 13 October 2021
1:30 PM - 5:30 PM
A107–A109
EVOLUTION OF POTASH MINING STRATEGIES IN THE US
Paper number: 229-9
Program: Technical Sessions
Time: 3:20 PM – 3:35 PM
Authors
-
Jeffrey MaukLakewood, CO
-
Nick KarlLakewood, CO
Abstract
As of 2020, calculated potash resources for current and potential mines where potash is the primary objective are: solution mining 903 Mt, conventional underground mining 222 Mt, alunite mining 71 Mt, and brine mining (including Great Salt Lake) 48 Mt. If we consider calculated potash resources for active mines only, they are: brine mining (including Great Salt Lake) 42 Mt, conventional underground mining 30 Mt, and solution mining 6 Mt. Note that brine resources are often underreported due to their dependence on recharge from meteoric waters and may be greatly affected by climate change. These data suggest that for the U.S. to reduce its dependence on potash imports and maintain its >5.5 Mt consumption per year, it will need to continue to develop less conventional resources.
Geological Society of America Abstracts with Programs. Vol. 53, No. 6
doi: 10.1130/abs/2021AM-366443
© Copyright 2021 The Geological Society of America (GSA), all rights reserved. Permission is hereby granted to the author(s) of this abstract to reproduce and distribute it freely, for noncommercial purposes. Permission is hereby granted to any individual scientist to download a single copy of this electronic file and reproduce up to 20 paper copies for noncommercial purposes advancing science and education, including classroom use, providing all reproductions include the complete content shown here, including the author information. All other forms of reproduction and/or transmittal are prohibited without written permission from GSA Copyright Permissions.